Relevant matters in construction contracts
Relevant matters are referred to in some construction contracts, such as JCT contracts. A relevant matter is a matter for which the client is responsible that materially affects the progress of the works. This may enable the contractor to claim direct loss and / or expense that has been incurred. Relevant matters might include:
- Failure to give the contractor possession of the site.
- Failure to give the contractor access to and from the site.
- Delays in receiving instructions.
- Opening up works or testing works that then prove to have been carried out in accordance with the contract.
- Discrepancies in the contract documents.
- Disruption caused by works being carried out by the client.
- Failure by the client to supply goods or materials.
- Instructions relating to variations and expenditure of provisional sums.
- Inaccurate forecasting of works described by approximate quantities.
- Issues relating to CDM.
Relevant matters should not be confused with relevant events. A relevant event is an event that causes a delay to the completion date, which is caused by the client, or is a neutral event not caused by either party. Relevant events entitle the contractor to claim an extension of time; that is for the completion date to be moved. A relevant event does not necessarily entitle the contractor to claim loss and expense. Similarly, a relevant matter need not necessarily result in a delay to the completion date, and so may not always entitle the contractor to an extension of time.
NEC contracts deal with these issues under the single heading ‘compensation events’. They do not treat compensation events as an allocation of blame, but rather an allocation of risk. Any risk that is not specifically identified as being attributed to the client is borne by the contractor.
The Society of Construction Law Delay and Disruption Protocol, 2nd edition, refers to an event or cause of delay or disruption which under the contract is at the risk and responsibility of the employer, as an 'employer risk event'.
[edit] Related articles on Designing Buildings Wiki
- Compensation event.
- Consideration.
- Delays on construction projects.
- Extension of time.
- Liquidated damages.
- Loss and expense.
- Provisional sum.
- Relevant event.
- Relevant event v relevant matter.
[edit] External References
Featured articles and news
Electrotechnical excellence, now open for entries.
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
New project and cultural district described in detail.
The nature of EPCs, crticism and inaccuracies.
History, issues and redesign.
From waste recycling to energy performance the hierchy.
An introduction to WERCS and WEEE responsibilities
Dealing with 2 million tonnes of waste equipment a year.
Global BACS Market: analytics and optimisation
A BSRIA glance at building automation and control systems.
What it is and how to use it.
Types of insulating plaster by binder and insulant.
Investors in People: CIOB achieves gold
Reflecting a commitment to employees and members.
Scratching beneath the surface; a guide to selection.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.
For the World Autism Awareness Month of April.